What does the order cost?

Run a backlog one job at a time and every job bleeds its cost of delayWhat it costs you per week to not have this yet — lost revenue, carried risk, a promise going stale. The same number that feeds WSJF. for every week it sits unfinished. So the sequence sets the total bill — and the cheapest order isn't “biggest first”. Weighted Shortest Job First — cost of delay ÷ duration — is provablySmith's rule (1956): sequencing by the ratio of weight to processing time minimises the total weighted completion time. WSJF is this rule applied to a backlog. the least-cost sequence.

1.1
1.2
4.0
1.0
4.0
lower is better
SequenceTotal delay cost
As plannedthe order in your backlog
400
Biggest firsthighest cost of delay first
363
Shortest firstquickest jobs first
283
WSJFcost of delay ÷ durationcheapest
277
Cost of delay still bleeding
week 051015week 19
As planned — area is its costWSJF frontier
31%cheaper than the plan

Running this backlog WSJF-first costs 277 in delay, against 400 for the planned order — 123 saved, the same work in the same weeks, just resequenced.

1Checkout fixwk 2 · CoD 8
2Search tweakwk 3 · CoD 4
3Reporting revampwk 8 · CoD 6
4Compliance auditwk 16 · CoD 9
5Email digestwk 19 · CoD 3

Read left to right: WSJF front-loads the jobs that bleed the most cost of delay per week of work, so the costliest waiting ends soonest. “Biggest first” looks responsible but parks a long job up front where it blocks every quick win behind it — which is why it's usually the dearest order of the four.

Smith's rule / Weighted Shortest Job First — costs are relative, only meaningful next to each other